Updated Project Schedule and Budget

July 30 2015

The project schedule has been revised to reflect delays in the fabrication and delivery of steel for the movable section of the new bridge. As a result of delays, the bridge is now expected to open to traffic in the spring of 2017, with final project completion including the decommissioning of the existing bridge expected in the fall of 2017.

The budget for the project has also been revised to $96.8 million, including a recently approved additional $2.554 million for necessary professional consulting services, habitat compensation, and legal costs. The City will seek to recover many of the costs resulting from steel fabrication and construction delays through the mediation process currently underway between the City, PCL, and MMM Group.

 