July Quarterly Update

July 22 2015

Quarterly reports are prepared on the Johnson Street Bridge Replacement Project throughout the year to keep Council and the community updated on this important project. The third quarterly report for 2015 was presented to Council on Thursday, July 16.

Since the update on May 7, 2015, the project schedule has been revised to reflect delays in the delivery of the structural steel.  The schedule has been updated to reflect  spring 2017 as the timeframe the new bridge will open to traffic and open for public use, with a final project completion timeframe of fall 2017.

The approved budget for the Johnson Street Bridge Project is $94.3 million. Council has directed staff to request funds as required. Potential additional costs have been identified at an estimated $3.858 million.

There remain a number of unresolved issues including costs of fendering, public realm, claim for additional professional consulting services, legal, mediator, and additional material costs.

For the full Quarterly Report, click here

 

 